Bridges25AA0020

BRIDGE PROGRAM - REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, TULNAGAN BR. 2 (B04887LZ) ALONG MANILA NORTH RD

BRIDGE PROGRAM - REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, TULNAGAN BR. 2 (B04887LZ) ALONG MANILA NORTH RD is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱23,642,424.66. Status: Past target date (DPWH On-Going). Contractor on record: TIJ CONST INC. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Malaggao, Adams, Ilocos Norte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Ilocos Norte 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

14 projects · ₱272.9M total · 0 flags

4. Implementation

Contract Amount

₱23,642,424.66

Progress

Past target date (DPWH On-Going)

Start Date

March 7, 2025

Target End

July 1, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.