Construction of Flood Mitigation Structure24FD0037

Construction of Flood Mitigation Structure along Colacling River, Bulawan Jr., Lupi, Camarines Sur

Construction of Flood Mitigation Structure along Colacling River, Bulawan Jr., Lupi, Camarines Sur is a DPWH-tracked public work in LUPI (CAMARINES SUR), CAMARINES SUR, Region V. Reported contract value: ₱96,494,439.77. Status: Reported complete (DPWH). Contractor on record: RAPIDWORKZ CONST & SUPPLY / STEVEN CONST & SUPPLY. Figures trace to sumbong.

LUPI (CAMARINES SUR), CAMARINES SUR, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Burabod Creek, Tigaon, Camarines Sur
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-24-0019960

₱22,000,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROV-24-0010957

₱1,398,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROV-24-0010958

₱129,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱96,494,439.77

Progress

Reported complete (DPWH)

Start Date

March 25, 2024

Target End

March 17, 2025

5. Audit