Construction of Drainage Structure22OA0101

Construction of Box Culvert along C. Arellano and Sacristia St., Malabon City

Construction of Box Culvert along C. Arellano and Sacristia St., Malabon City is a DPWH-tracked public work in CITY OF MALABON (METROPOLITAN MANILA), MALABON CITY, National Capital Region. Reported contract value: ₱14,846,141.76. Status: Reported complete (DPWH). Contractor on record: ROTAFLEX CONST AND DEVELOPMENT CORP FORMERLY:ROTA FLEX CONST. Figures trace to sumbong.

CITY OF MALABON (METROPOLITAN MANILA), MALABON CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Floodgates along Navotas Coastal Dike, Navotas City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003178

₱633,500,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002645

₱224,500,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002943

₱100,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002648

₱40,615,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001963

₱35,500,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

77 projects · ₱2.8B total · 6 flags

4. Implementation

Contract Amount

₱14,846,141.76

Progress

Reported complete (DPWH)

Start Date

March 24, 2022

Target End

May 4, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.