Buildings and Facilities20CJ0139

LOCAL INFRASTRUCTURE PROGRAM CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BRGY. SAN PASCUAL, TARLAC CITY, TARLAC

LOCAL INFRASTRUCTURE PROGRAM CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BRGY. SAN PASCUAL, TARLAC CITY, TARLAC is a DPWH-tracked public work in Tarlac DEO, Region III. Reported contract value: ₱4,850,986.53. Status: Reported complete (DPWH). Contractor on record: 3-SIDES BUILDERS. Figures trace to dpwh.

Tarlac DEO, Region III
Region: Region III

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

42 projects · ₱631.2M total · 0 flags

Other projects by this contractor

No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG); SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATIGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF REINFORCED CONCRETE SLOPE PROTECTION WITH STEEL SHEET PILES ALONG SAPANGBALEN RIVER, B

Pampanga 3rd DEO, Region III

2025₱47.9M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG); SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATIGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF REINFORCED CONCRETE SLOPE PROTECTION WITH STEEL SHEET PILES ALONG SAPANGBALEN RIVER, BR

Pampanga 3rd DEO, Region III

2025₱47.9M
Ongoing (DPWH-reported)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PAMPANGA RIVER, (DOWNSTREAM- LEFT BANK) BARANGAY CONSUELO, MACABEBE, PAMP

Pampanga 1st DEO, Region III

2025₱46.5M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PAMPANGA RIVER, (DOWNSTREAM- RIGHT BANK) BARANGAY CONSUELO, MACABEBE, PAMP

Pampanga 1st DEO, Region III

2025₱46.5M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM - CONSTRUCTION/REPAIR/ REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS -LOCAL ROADS AND BRIDGES - LOCAL BRIDGES -CONSTRUCTION/REHABILITATION OF SAN JUAN BRIDGE ALONG OLD NATIONAL ROAD, SAMAL, BATAAN

Bataan 1st DEO, Region III

2021₱44.1M
Reported complete (DPWH)
No sat.

SIPAG-ACCESS ROADS AND/OR BRIDGE/S LEADING TO MAJOR/STRATIGIC PUBLIC BUILDINGS/FACILITIES- IMPROVEMENT/REHABILITATION OF PANDAN BRIDGE, ANGELES CITY

Pampanga 3rd DEO, Region III

2023₱37.2M
Reported complete (DPWH)
View all 42 projects →

4. Implementation

Contract Amount

₱4,850,986.53

Progress

Reported complete (DPWH)

Start Date

October 16, 2020

Target End

January 13, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.