Flood Control and Drainage20AH0101

CONSTRUCTION OF DRAINAGE SYSTEM,BRGY. SAN GUILLERMO,SAN JACINTO,PANGASINAN

CONSTRUCTION OF DRAINAGE SYSTEM,BRGY. SAN GUILLERMO,SAN JACINTO,PANGASINAN is a DPWH-tracked public work in Pangasinan 2nd DEO, Region I. Reported contract value: ₱1,458,270.00. Status: Reported complete (DPWH). Contractor on record: MIGHTYWAY CONST AND SUPPLY. Figures trace to dpwh.

Pangasinan 2nd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱3,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Dagupan City, Pangasinan
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Pangasinan 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱1,458,270.00

Progress

Reported complete (DPWH)

Start Date

February 12, 2020

Target End

April 30, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.