Construction of Flood Mitigation Structure22DI0043

Construction of Flood Mitigation Structure, Barangay Sto. Tomas, Biñan City, Laguna

Construction of Flood Mitigation Structure, Barangay Sto. Tomas, Biñan City, Laguna is a DPWH-tracked public work in CITY OF BIÑAN (LAGUNA), LAGUNA, Region IV-A. Reported contract value: ₱49,494,593.92. Status: Reported complete (DPWH). Contractor on record: MAR-VEL CONST & SUPPLY. Figures trace to sumbong.

CITY OF BIÑAN (LAGUNA), LAGUNA, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 97%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay Sto. Tomas, Bi±an City, Laguna
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002907

₱1,026,969,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003022

₱159,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-22-0007547

₱51,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002753

₱40,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱49,494,593.92

Progress

Reported complete (DPWH)

Start Date

February 14, 2022

Target End

October 2, 2022