Flood Control and Drainage19L00020

CONST. OF FLOOD MITIGATION STRUCTURE-FLOOD CONTROL STRUCTURE ALONG MALAGAMOT ROAD-JCT. MUDIANG ROAD,

CONST. OF FLOOD MITIGATION STRUCTURE-FLOOD CONTROL STRUCTURE ALONG MALAGAMOT ROAD-JCT. MUDIANG ROAD, is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱88,981,371.05. Status: Reported complete (DPWH). Contractor on record: MONOLITHIC CONST. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱88,981,371.05

Progress

Reported complete (DPWH)

Start Date

July 26, 2019

Target End

August 12, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.