Bridges21PE0008

REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES: ASOKONG BR. (B02666LZ) ALONG CONG. ANDRES ACOP COSALAN RD, K0337+031, KABAYAN, BENGUET

REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES: ASOKONG BR. (B02666LZ) ALONG CONG. ANDRES ACOP COSALAN RD, K0337+031, KABAYAN, BENGUET is a DPWH-tracked public work in Benguet 1st DEO, Cordillera Administrative Region. Reported contract value: ₱904,904.85. Status: Reported complete (DPWH). Contractor on record: EFLER CONST AND ENT 41046. Figures trace to dpwh.

Benguet 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure within Agno River Basin: along Agno River Main (Pacso), Sta. 209 + 980 - Sta. 210 + 610, Kabayan, Benguet
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Benguet 1st DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 41046

59 projects · ₱614.8M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF PROPER GADANG-LAO-ANGAN ROAD, KAPANGAN, BENGUET

Benguet 2nd DEO, Cordillera Administrative Region

2024₱95.3M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE WITHIN AGNO RIVER BASIN: ALONG AGNO RIVER LAPALAP SECTION, STA. 10+802 - STA. 11+162 (BS), BUGUIAS, BENGUET

Benguet 2nd DEO, Cordillera Administrative Region

2025₱41.1M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF 4 STOREY 8 CLASSROOM SCHOOL BUILDING, LAM-AYAN INTEGRATED SCHOOL, BUGUIAS, BENGUET

Benguet 2nd DEO, Cordillera Administrative Region

2024₱39.8M
Past target date (DPWH On-Going)
No sat.

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS: GOV. BADO DANGWA NATIONAL RD - K0291+570 - K0291+670, K0292+136 - K0292+290, K0292+445 - K0292+520

Benguet 2nd DEO, Cordillera Administrative Region

2025₱38.8M
Past target date (DPWH On-Going)
No sat.

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE: BAGUIO- BONTOC ROAD - K0266+600 - K0266+700, K0267+150 - K0267+180, K0268+850 - K0268+920, K0270+015 - K0270+045, K0272+713 - K0272+770, TUBLAY- ATOK, BENGUET

Benguet 2nd DEO, Cordillera Administrative Region

2023₱29.4M
Reported complete (DPWH)
No sat.

REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS: BAGUIO-BONTOC RD - K0266+500-K0266+525, K0266+600-K0266+605, K0269+568-K0269+578, K0269+677-K0269+690, K0270+017-K0270+043, K0270+700-K0270+720, K0270+833-K0270+860, K0270+

Benguet 2nd DEO, Cordillera Administrative Region

2025₱27.2M
Past target date (DPWH On-Going)
View all 59 projects →

4. Implementation

Contract Amount

₱904,904.85

Progress

Reported complete (DPWH)

Start Date

March 25, 2021

Target End

April 23, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.