Buildings and Facilities21DQ0118

CONSTRUCTION/COMPLETION OF 4STY8CL, V.P. VILLANUEVA MS (PALAPALA), DASMARIÑAS, CAVITE; CONSTRUCTION/COMPLETION OF 4STY16CL, PALIPARAN II NATIONAL HIGH SCHOOL - CONGRESSIONAL ANNEX, DASMARIÑAS, CAVITE; CONSTRUCTION/COMPLETION OF 4STY12CL, DASMARIÑAS II

CONSTRUCTION/COMPLETION OF 4STY8CL, V.P. VILLANUEVA MS (PALAPALA), DASMARIÑAS, CAVITE; CONSTRUCTION/COMPLETION OF 4STY16CL, PALIPARAN II NATIONAL HIGH SCHOOL - CONGRESSIONAL ANNEX, DASMARIÑAS, CAVITE; CONSTRUCTION/COMPLETION OF 4STY12CL, DASMARIÑAS II is a DPWH-tracked public work in Cavite 3rd DEO, Region IV-A. Reported contract value: ₱17,143,648.68. Status: Reported complete (DPWH). Contractor on record: T E TRINIDAD CONST. Figures trace to dpwh.

Cavite 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structures and Drainage Systems along Bacoor Boulevard Road (Northbound) K0017 + 427 - K0016 + (-659) with exceptions, Bacoor City, Cavite
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Cavite 3rd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

79 projects · ₱1.0B total · 0 flags

Other projects by this contractor

View all 79 projects →

4. Implementation

Contract Amount

₱17,143,648.68

Progress

Reported complete (DPWH)

Start Date

November 15, 2021

Target End

May 13, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.