Buildings and Facilities17CE0229

CONSTRUCTION OF 6 CLASSROOMS WORKSHOP BUILDING, STA. MARIA NATIONAL HIGH SCHOOL, LICAB, NUEVA ECIJA

CONSTRUCTION OF 6 CLASSROOMS WORKSHOP BUILDING, STA. MARIA NATIONAL HIGH SCHOOL, LICAB, NUEVA ECIJA is a DPWH-tracked public work in Nueva Ecija 1st DEO, Region III. Reported contract value: ₱31,382,350.48. Status: Reported complete (DPWH). Contractor on record: DGSARM BUILDERS INC FORMERLY: D G SARMENTA CONST. Figures trace to dpwh.

Nueva Ecija 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱46,364,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Repair/Rehabilitation of Flood Control Dikes, Sta. 3+479 - Sta. 3+901, Brgy. Aquino, Licab, Nueva Ecija
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Agency-level releases for FY2017, not tied to this contract

Nueva Ecija 1st DEO · SARO 1,101 (₱106,257,715,220.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱31,382,350.48

Progress

Reported complete (DPWH)

Start Date

January 11, 2018

Target End

September 17, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.