Roads20IA0074

CONSTRUCTION/REHABILITATION OF ROAD LEADING TO UNGALI ELEMENTARY SCHOOL II

CONSTRUCTION/REHABILITATION OF ROAD LEADING TO UNGALI ELEMENTARY SCHOOL II is a DPWH-tracked public work in Biliran DEO, Region VIII. Reported contract value: ₱1,925,120.00. Status: Reported complete (DPWH). Contractor on record: ROVING PREMIER CONTRACTORS INC. Figures trace to dpwh.

Biliran DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Ungali Flood Control along Biliran Circumferential Road, Kawayan, Biliran
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Biliran DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱1,925,120.00

Progress

Reported complete (DPWH)

Start Date

October 15, 2020

Target End

January 12, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.