Flood Control and Drainage17OF0077

IMPROVEMENT OF MALABON-TULLAHAN RIVER, BRGY. SAN BARTOLOME (PHASE V), QUEZON CITY

IMPROVEMENT OF MALABON-TULLAHAN RIVER, BRGY. SAN BARTOLOME (PHASE V), QUEZON CITY is a DPWH-tracked public work in Quezon City 1st DEO, National Capital Region. Reported contract value: ₱78,133,202.50. Status: Past target date (DPWH On-Going). Contractor on record: L R TIQUI BUILDERS INC. Figures trace to dpwh.

Quezon City 1st DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structures Tributaries at Brgy. Commonwealth, Quezon City
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-17-0021010

₱300,000,000.00 · FY2017

Released to Regional Field Unit - V (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

380 projects · ₱29.1B total · 8 flags

Other projects by this contractor

View all 380 projects →

4. Implementation

Contract Amount

₱78,133,202.50

Progress

Past target date (DPWH On-Going)

Start Date

August 3, 2017

Target End

July 28, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.