Buildings and Facilities23PI0026

CONSTRUCTION (COMPLETION) OF THE EXTENSION (ANNEX) BUILDING OF DPWH MOUNTAIN PROVINCE 1ST DEO, BONTOC, MOUNTAIN PROVINCE

CONSTRUCTION (COMPLETION) OF THE EXTENSION (ANNEX) BUILDING OF DPWH MOUNTAIN PROVINCE 1ST DEO, BONTOC, MOUNTAIN PROVINCE is a DPWH-tracked public work in Mountain Province 1st DEO, Cordillera Administrative Region. Reported contract value: ₱45,570,000.00. Status: Reported complete (DPWH). Contractor on record: E T LATAWAN CONST. Figures trace to dpwh.

Mountain Province 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Mitigation Structure, Sao-Malitep along Chico River, Balili, Bontoc, Mountain Province
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Mountain Province 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

49 projects · ₱2.1B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF CANAN BRIDGE, LA PAZ, ABRA

Abra DEO, Cordillera Administrative Region

2024₱140.2M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES-CONSTRUCTION OF CALABA VIADUCT PHASE I, CALABA, BANGUED, ABRA

Abra DEO, Cordillera Administrative Region

2024₱139.9M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES-CONSTRUCTION OF CALABA VIADUCT PHASE 2, CALABA, BANGUED, ABRA

Abra DEO, Cordillera Administrative Region

2024₱139.8M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF OTIP BRIDGE, TUBO, ABRA

Abra DEO, Cordillera Administrative Region

2024₱138.1M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES-CONSTRUCTION OF SINALANG-PALAO BRIDGE APPROACHES, PALAO, BANGUED, ABRA

Abra DEO, Cordillera Administrative Region

2024₱137.5M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES-CONSTRUCTION OF SINALANG-PALAO BRIDGE, BANGUED, ABRA

Abra DEO, Cordillera Administrative Region

2024₱137.4M
Past target date (DPWH On-Going)
View all 49 projects →

4. Implementation

Contract Amount

₱45,570,000.00

Progress

Reported complete (DPWH)

Start Date

February 20, 2023

Target End

March 6, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.