Construction of Flood Mitigation Structure23I00007

Construction of Flood Control structure along Daguitan River Basin, Right Side Bank, Barangay Poblacion, District VI, Burauen, Leyte

Construction of Flood Control structure along Daguitan River Basin, Right Side Bank, Barangay Poblacion, District VI, Burauen, Leyte is a DPWH-tracked public work in BURAUEN (LEYTE), LEYTE, Region VIII. Reported contract value: ₱109,863,168.90. Status: Reported complete (DPWH). Contractor on record: FAIRCHILD BUILDERS & DEVELOPERS INC. Figures trace to sumbong.

BURAUEN (LEYTE), LEYTE, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱46,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Anonang River Basin, Barangay Anonang, Burauen, Leyte
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Leyte 2nd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

42 projects · ₱3.3B total · 2 flags

Other projects by this contractor

No sat.

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES CONSTRUCTION OF ROAD, BURAUEN, LEYTE

Region VIII, Region VIII

2022₱286.3M
Past target date (DPWH On-Going)
No sat.

CLUSTER 1: 1. CONSTRUCTION OF ROCK GUARD SLOPE PROTECTION ALONG BURAUEN - MAHAGNAO ROAD, K0988+780 - K0989+020, BURAUEN, LEYTE; AND TWO (2) OTHER LOCATIONS IN BURAUEN, LEYTE

Region VIII, Region VIII

2020₱283.4M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS - BURAUEN - MAHAGNAO RD. - K0989+685 - K0989+810, BURAUEN, LEYTE

Region VIII, Region VIII

2021₱144.7M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS - BURAUEN - MAHAGNAO RD. - K0989+560 - K0989+685, BURAUEN, LEYTE

Region VIII, Region VIII

2021₱144.7M
Reported complete (DPWH)
No sat.

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - ROAD OPENING AND CONCRETING OF BURAUEN SOUTHEAST SEMI-CIRCUMFERENTIAL ROAD TRAVERSING BRGY. POBLACION

Region VIII, Region VIII

2023₱144.7M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF (RCDG) REINFORCED CONCRETE DECK GIRDER BRIDGE FROM BARANGAY MAHAGN

Region VIII, Region VIII

2024₱144.7M
Past target date (DPWH On-Going)
View all 42 projects →

4. Implementation

Contract Amount

₱109,863,168.90

Progress

Reported complete (DPWH)

Start Date

March 15, 2023

Target End

March 13, 2024

5. Audit