Buildings and Facilities24NF0083

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY GARCIA, SANTA MONICA, SURIGAO DEL NORTE

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY GARCIA, SANTA MONICA, SURIGAO DEL NORTE is a DPWH-tracked public work in Surigao del Norte 1st DEO, Region XIII. Reported contract value: ₱1,977,994.00. Status: Reported complete (DPWH). Contractor on record: RADIAN CONST AND SUPPLY. Figures trace to dpwh.

Surigao del Norte 1st DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Tagbayani Flood Mitigation Structure, Barangay Tagbayani, Sison, Surigao del Norte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Surigao del Norte 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

210 projects · ₱1.3B total · 0 flags

4. Implementation

Contract Amount

₱1,977,994.00

Progress

Reported complete (DPWH)

Start Date

July 17, 2024

Target End

October 14, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.