Bridges23EE0043

REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES-NAGBARIL BRIDGE II (B00039CR)ALONG CORON-BUSUANGA ROAD CORON, PALAWAN

REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES-NAGBARIL BRIDGE II (B00039CR)ALONG CORON-BUSUANGA ROAD CORON, PALAWAN is a DPWH-tracked public work in Palawan 1st DEO, Region IV-B. Reported contract value: ₱4,899,997.04. Status: Reported complete (DPWH). Contractor on record: ALPHA VECTOR CONST AND SUPPLY. Figures trace to dpwh.

Palawan 1st DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱20,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Labangan Bridge I Flood Control Structure, Sta. 0 + 000 - Sta. 0 + 692, Coron, Palawan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Palawan 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

99 projects · ₱1.7B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF MANILA-BATANGAS - BUGTONG NA PULO - STAR TOLLWAY IN

Batangas 4th DEO, Region IV-A

2024₱144.0M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, MANILA-BATANGAS - BUGTONG NA PULO - STAR TOLLWAY INTERCHANGE PACKAGE C, BUGTONG NA PULO, LIPA CITY, BATANGA

Batangas 4th DEO, Region IV-A

2024₱140.4M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT PROGRAM- ROAD WIDENING- TERTIARY ROADS- CORON-BUSUANGA ROAD, K0059+866-K0061+205, CORON, PALAWAN

Region IV-B, Region IV-B

2023₱101.3M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF MANILA-BATANGAS - BUGTONG

Batangas 4th DEO, Region IV-A

2023₱96.5M
Reported complete (DPWH)

CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BANABA BRIDGE BUSUANGA, PALAWAN

Palawan 1st DEO, Region IV-B

2024₱96.5M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM- CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM- CONST. OF SLOPE PROTECTION STRUCTURE (KIWIT BR. 1), BUSUANGA, PALAWAN

Region IV-B, Region IV-B

2025₱72.5M
Past target date (DPWH On-Going)
View all 99 projects →

4. Implementation

Contract Amount

₱4,899,997.04

Progress

Reported complete (DPWH)

Start Date

February 15, 2023

Target End

April 18, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.