Water Provision and Storage16DJ0008

CONSTRUCTION OF WATER SUPPLY (LEVEL II) BRGY. PURY, SAN ANTONIO, QUEZON 2ND LD

CONSTRUCTION OF WATER SUPPLY (LEVEL II) BRGY. PURY, SAN ANTONIO, QUEZON 2ND LD is a DPWH-tracked public work in Quezon 2nd DEO, Region IV-A. Reported contract value: ₱1,875,254.16. Status: Reported complete (DPWH). Contractor on record: A M ABDON CONST. Figures trace to dpwh.

Quezon 2nd DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structures and Tributaries at Brgy. Payatas, (Phase 2) District II, Quezon City
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-16-0020569

₱358,949.00 · FY2016

Released to 00 - Don Mariano Marcos Memorial State University To cover re (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

43 projects · ₱173.2M total · 0 flags

4. Implementation

Contract Amount

₱1,875,254.16

Progress

Reported complete (DPWH)

Start Date

March 14, 2016

Target End

July 11, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.