Construction of Drainage Structure24EI0046

Construction of Drainage Canal, Barangay Maujao, Bulalacao, Oriental Mindoro

Construction of Drainage Canal, Barangay Maujao, Bulalacao, Oriental Mindoro is a DPWH-tracked public work in BULALACAO (SAN PEDRO) (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B. Reported contract value: ₱4,947,019.45. Status: Reported complete (DPWH). Contractor on record: SOSEP BUILDERS. Figures trace to sumbong.

BULALACAO (SAN PEDRO) (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Possible match · score 78%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Baugo Flood Control Structure, Bontoc, Southern Leyte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0004024

₱237,954.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0002609

₱25,000,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008398

₱128,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0004305

₱193,512.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-24-0020130

₱20,000,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0006527

₱5,615,052.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008383

₱1,386,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0004004

₱564,186.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0006528

₱521,819.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

Possible match · 83%

Construction of Covered Court at Batong Dalig, Soc

₱2,490,719.59 · SOSEP BUILDERS

Possible match · 81%

Concreting of Road at Malayong, Gloria, Oriental M

₱1,739,415.87 · SOSEP BUILDERS

Possible match · 80%

Concreting of Road at Sitio Pocanil, San Roque, Bu

₱1,987,771.71 · SOSEP BUILDERS

Possible match · 78%

Concreting of Road at Tambong, Gloria, Oriental Mi

₱996,023.09 · SOSEP BUILDERS

Possible match · 78%

Construction of Fence of Barangay Hall at Canubing

₱492,718.02 · SOSEP BUILDERS

4. Implementation

Contract Amount

₱4,947,019.45

Progress

Reported complete (DPWH)

Start Date

February 2, 2024

Target End

May 16, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.