Roads21CC0187

ASPHALT OVERLAY ALONG BALIUAG-BUSTOS ROAD, A. KM51+103 - KM51+002, B. KM51+284 - KM52+126, BULACAN

ASPHALT OVERLAY ALONG BALIUAG-BUSTOS ROAD, A. KM51+103 - KM51+002, B. KM51+284 - KM52+126, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱28,949,996.35. Status: Reported complete (DPWH). Contractor on record: 729 CONST INC FORMERLY 722 CONST INC. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Gatbuca, Calumpit, Bulacan
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Bulacan 1st DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Asphalt Overlay along Baliuag - Bustos Road a.km51

₱28,807,363.65 · 729 CONSTRUCTION, . (FORMERLY: 722 CONSTRUCTION, .)

Contractor

B

231 projects · ₱7.1B total · 9 flags

4. Implementation

Contract Amount

₱28,949,996.35

Progress

Reported complete (DPWH)

Start Date

December 15, 2021

Target End

January 13, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.