Flood Control and Drainage24N00146

CONSTRUCTION OF FLOOD CONTROL STRUCTURE-LOWER AGUSAN DEVELOPMENT PROJECT, FLOOD CONTROL COMPONENT, STAGE 1, PHASE 1&2, URBAN DRAINAGE SYSTEM IN BUTUAN CITY (MANDACPAN-BONBON CHANNEL IMPROVEMENT, DOWNSTREAM), PACKAGE 2, BUTUAN CITY, AGUSAN DEL NORTE

CONSTRUCTION OF FLOOD CONTROL STRUCTURE-LOWER AGUSAN DEVELOPMENT PROJECT, FLOOD CONTROL COMPONENT, STAGE 1, PHASE 1&2, URBAN DRAINAGE SYSTEM IN BUTUAN CITY (MANDACPAN-BONBON CHANNEL IMPROVEMENT, DOWNSTREAM), PACKAGE 2, BUTUAN CITY, AGUSAN DEL NORTE is a DPWH-tracked public work in Region XIII, Region XIII. Reported contract value: ₱192,999,999.41. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: EQUI-PARCO CONST CO. Figures trace to dpwh.

Region XIII, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

725 projects · ₱77.9B total · 5 flags

4. Implementation

Contract Amount

₱192,999,999.41

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

May 17, 2024

Target End

August 16, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.