Roads21PF0049

IMPROVEMENT OF LOCAL ROAD, SIPITAN SICGATAN FMR, BARANGAY DALIPEY, BAKUN, BENGUET, STA. 8+707 9+590

IMPROVEMENT OF LOCAL ROAD, SIPITAN SICGATAN FMR, BARANGAY DALIPEY, BAKUN, BENGUET, STA. 8+707 9+590 is a DPWH-tracked public work in Benguet 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱9,890,022.68. Status: Reported complete (DPWH). Contractor on record: FMCWARRIORS CONST FORMERLY: TINGLAWAN GEN CONST. Figures trace to dpwh.

Benguet 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Ampusongan Flood Control Phase 2, Barangay Ampusongan, Bakun, Benguet
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Benguet 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱9.9M total · 0 flags

4. Implementation

Contract Amount

₱9,890,022.68

Progress

Reported complete (DPWH)

Start Date

May 12, 2021

Target End

August 21, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.