Roads21BJ0016

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS ARITAO-QUIRINO ROAD-K0258+405 - K0258+414, K0280+156-K0280+192, K0286+053-K0286+058, K0291+180-K0291+189 KASIBU, NUEVA VIZCAYA

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS ARITAO-QUIRINO ROAD-K0258+405 - K0258+414, K0280+156-K0280+192, K0286+053-K0286+058, K0291+180-K0291+189 KASIBU, NUEVA VIZCAYA is a DPWH-tracked public work in Nueva Vizcaya 2nd DEO, Region II. Reported contract value: ₱1,500,354.12. Status: Reported complete (DPWH). Contractor on record: 4KIDS BUILDERS AND CONST SUPPLY. Figures trace to dpwh.

Nueva Vizcaya 2nd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement of Flood Control and Drainage Structure along Sta. Cruz River, Salinas Section 1, Bambang, Nueva Vizcaya
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Nueva Vizcaya 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

14 projects · ₱61.4M total · 0 flags

4. Implementation

Contract Amount

₱1,500,354.12

Progress

Reported complete (DPWH)

Start Date

July 1, 2021

Target End

August 20, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.