Roads18IJ0152

REHABILITATION/IMPROVEMENT OF BARANGAY CAGSUMJE - BARANGAY ARAPISON, STA. MARGARITA, SAMAR

REHABILITATION/IMPROVEMENT OF BARANGAY CAGSUMJE - BARANGAY ARAPISON, STA. MARGARITA, SAMAR is a DPWH-tracked public work in Samar 1st DEO, Region VIII. Reported contract value: ₱8,915,040.00. Status: Reported complete (DPWH). Contractor on record: SFORT BUILDERS 41222. Figures trace to dpwh.

Samar 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱8,915,040.00

Progress

Reported complete (DPWH)

Start Date

July 2, 2018

Target End

September 29, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.