Flood Control and Drainage24IM0135

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BURAYAN RIVER, TACLOBAN CITY

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BURAYAN RIVER, TACLOBAN CITY is a DPWH-tracked public work in Tacloban City DEO, Region VIII. Reported contract value: ₱48,188,053.00. Status: Past target date (DPWH On-Going). Contractor on record: R YAO CONST. Figures trace to dpwh.

Tacloban City DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure ( Drainage ) , barangay 62 - B, Tacloban City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Tacloban City DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱48,188,053.00

Progress

Past target date (DPWH On-Going)

Start Date

May 28, 2025

Target End

January 1, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.