Construction of Flood Mitigation Structure24CI0021

Construction of Flood Control Structure in Angeles City, Pampanga (Phase 2)

Construction of Flood Control Structure in Angeles City, Pampanga (Phase 2) is a DPWH-tracked public work in ANGELES CITY (PAMPANGA), PAMPANGA, Region III. Reported contract value: ₱48,247,379.40. Status: Reported complete (DPWH). Contractor on record: B-12 CONST AND TRADING CORP. Figures trace to sumbong.

ANGELES CITY (PAMPANGA), PAMPANGA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Pampanga River, Apalit, Pampanga
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0008254

₱1,156,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0017639

₱458,088.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-24-0018104

₱90,000,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0018317

₱121,051.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0008256

₱107,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0008158

₱156,487.00 · FY2024

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

164 projects · ₱8.7B total · 0 flags

Other projects by this contractor

No sat.

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS-JOSE ABAD SANTOS AVENUE (JASA), PROVINCE OF PAMPANGA

Region III, Region III

2023₱156.3M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM-REHABILITITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS, JOSE ABAD SANTOS AVENUE (JASA), PROVINCE OF PAMPANGA

Region III, Region III

2020₱151.1M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS / FACILITIES - REHABILITATION OF STA. ANA - MAGALANG ROAD (SAN PABLO - ARENAS PORTION) PHASE I,

Pampanga 1st DEO, Region III

2025₱137.5M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF DEL ROSARIO - CALULUT ROAD, CITY OF SAN FERNANDO, PAMPANGA

Pampanga 1st DEO, Region III

2025₱137.5M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT-ROAD WIDENING-PRIMARY ROADS, JOSE ABAD SANTOS AVENUE (JASA), PAMPANGA 2ND LEGISLATIVE DISTRICT, PROVINCE OF PAMPANGA

Region III, Region III

2018₱132.6M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - MALINO - SUCLABAN BYPASS ROAD, CITY OF SAN FERNANDO, PAMPANGA

Pampanga 1st DEO, Region III

2025₱130.7M
Past target date (DPWH On-Going)
View all 164 projects →

4. Implementation

Contract Amount

₱48,247,379.40

Progress

Reported complete (DPWH)

Start Date

February 12, 2024

Target End

August 6, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.