Water Provision and Storage23AA0043

CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS-WATER SUPPLY SYSTEMCONSTRUCTION OF WATER SYSTEM (LEVEL III), BRGY. SAOIT, PAGALI, PAAYAS, ABLAN, BAYOG, BUDUAN & POBLACION, BURGOS, ILOCOS NORTE

CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS-WATER SUPPLY SYSTEMCONSTRUCTION OF WATER SYSTEM (LEVEL III), BRGY. SAOIT, PAGALI, PAAYAS, ABLAN, BAYOG, BUDUAN & POBLACION, BURGOS, ILOCOS NORTE is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱18,994,606.11. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: VILLAR GEN CONST AND SUPPLIES. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Project (Nagsanga and Pragata Section), Pasuquin, Ilocos Norte
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Ilocos Norte 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

493 projects · ₱8.0B total · 42 flags

4. Implementation

Contract Amount

₱18,994,606.11

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 13, 2023

Target End

April 28, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.