Construction of Flood Mitigation Structure24IJ0070

Construction of Flood Control Structure Brgy Canlapwas, Pagsanghan, Samar

Construction of Flood Control Structure Brgy Canlapwas, Pagsanghan, Samar is a DPWH-tracked public work in PAGSANGHAN (SAMAR (WESTERN SAMAR)), SAMAR (WESTERN SAMAR), Region VIII. Reported contract value: ₱19,777,562.05. Status: Reported complete (DPWH). Contractor on record: ETAN CONST. Figures trace to sumbong.

PAGSANGHAN (SAMAR (WESTERN SAMAR)), SAMAR (WESTERN SAMAR), Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure Brgy Canlapwas, Pagsanghan, Samar
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0007018

₱70,000,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0006417

₱4,865,401.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0007563

₱1,441,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0006418

₱446,155.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0007560

₱133,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

138 projects · ₱4.2B total · 0 flags

4. Implementation

Contract Amount

₱19,777,562.05

Progress

Reported complete (DPWH)

Start Date

June 3, 2024

Target End

December 19, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.