Buildings and Facilities17PC0108

PACKAGE IV. 1.) CONSTRUCTION OF BAGUTONG ES 1 STOREY 2 CL, 2.) CONSTRUCTION OF EMILIANA ES 1 STOREY 2CL

PACKAGE IV. 1.) CONSTRUCTION OF BAGUTONG ES 1 STOREY 2 CL, 2.) CONSTRUCTION OF EMILIANA ES 1 STOREY 2CL is a DPWH-tracked public work in Apayao 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱5,385,660.85. Status: Reported complete (DPWH). Contractor on record: ARESEF ENGINEERING. Figures trace to dpwh.

Apayao 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 73%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Yawa Flood Control, Legazpi City, Albay
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-17-0001304

₱350,000.00 · FY2017

Released to Taft National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

12 projects · ₱59.2M total · 0 flags

4. Implementation

Contract Amount

₱5,385,660.85

Progress

Reported complete (DPWH)

Start Date

December 27, 2017

Target End

May 25, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.