Flood Control and Drainage21K00118

CONST. OF BARA-AS FLOOD CONTROL MITIGATION AT BARA-AS RIVER,PICONG, LANAO DEL SUL

CONST. OF BARA-AS FLOOD CONTROL MITIGATION AT BARA-AS RIVER,PICONG, LANAO DEL SUL is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱46,798,585.21. Status: Reported complete (DPWH). Contractor on record: M M A ACHIEVER CONST. Figures trace to dpwh.

Region X, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱46,798,585.21

Progress

Reported complete (DPWH)

Start Date

March 26, 2021

Target End

October 21, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.