Construction of Flood Mitigation Structure24PD0027

Construction of Flood Mitigation Structure along Balili River (Tributaries) (Sta 0+620 - Sta 0+793), Baguio City

Construction of Flood Mitigation Structure along Balili River (Tributaries) (Sta 0+620 - Sta 0+793), Baguio City is a DPWH-tracked public work in BAGUIO CITY (BENGUET), BENGUET, Cordillera Administrative Region. Reported contract value: ₱49,000,000.00. Status: Reported complete (DPWH). Contractor on record: GOLDRICH CONST & TRADING. Figures trace to sumbong.

BAGUIO CITY (BENGUET), BENGUET, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Probable match · score 94%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Balili River ( Tributaries ) ( Sta 0 + 620 - Sta 0 + 793 ) , Baguio City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-CAR-24-0000996

₱754,751.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-CAR-24-0005881

₱524,142.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-CAR-24-0008542

₱1,455,533.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-CAR-24-0008543

₱134,374.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-CAR-24-0015326

₱25,686.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-CAR-24-0002558

₱196,854.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

13 projects · ₱801.6M total · 3 flags

4. Implementation

Contract Amount

₱49,000,000.00

Progress

Reported complete (DPWH)

Start Date

March 15, 2024

Target End

November 13, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.