Roads23FO0097

BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR / STRATEGIC PUBLIC BUILDINGS / FACILITIES - CONSTRUCTION OF MALAMA - TUPAS ROAD, LIGAO CITY, ALBAY

BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR / STRATEGIC PUBLIC BUILDINGS / FACILITIES - CONSTRUCTION OF MALAMA - TUPAS ROAD, LIGAO CITY, ALBAY is a DPWH-tracked public work in Albay 3rd DEO, Region V. Reported contract value: ₱45,354,458.15. Status: Reported complete (DPWH). Contractor on record: RMH CONST. Figures trace to dpwh.

Albay 3rd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Tobgon Flood Mitigation Structure, Ligao City, Albay
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Albay 3rd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱45,354,458.15

Progress

Reported complete (DPWH)

Start Date

December 4, 2023

Target End

July 30, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.