Bridges20KG0099

REPAIR OF DAMAGED OVERFLOW SUBMARINE BRIDGE FLOORING AND CLEARING OF WATERWAYS ALONG SALVADOR-SAPAD-NUNUNGAN ROAD,PUTIDON,SALVADOR,LDN

REPAIR OF DAMAGED OVERFLOW SUBMARINE BRIDGE FLOORING AND CLEARING OF WATERWAYS ALONG SALVADOR-SAPAD-NUNUNGAN ROAD,PUTIDON,SALVADOR,LDN is a DPWH-tracked public work in Lanao del Norte 2nd DEO, Region X. Reported contract value: ₱2,533,294.68. Status: Reported complete (DPWH). Contractor on record: AL-AMEN BUILDERS. Figures trace to dpwh.

Lanao del Norte 2nd DEO, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-F-19-0025223

₱1,633,569.00 · FY2019

Released to Mindanao State University - Marawi Ad (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

74 projects · ₱1.8B total · 0 flags

Other projects by this contractor

No sat.

INSTALLATION OF SOLAR LED STREETLIGHTS WITHIN BARANGAYS 649 TO 828, PRES. QUIRINO AVE (FROM TAFT AVE. TO SOUTH SUPERHIGHWAY), SOUTH SUPERHIGHWAY (FROM ZOBEL ROXAS ST. TO P. QUIRINO AVE), P. FAURA ST. (SAN MARCELINO ST. TO ROXAS BLVD.), ESCODA ST. (FROM TA

South Manila DEO, National Capital Region

2025₱145.2M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2:PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS-FLOOD MGM'T PROGRAM-CONST./MAINT. OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS-CONST. OF SLOPE PROTECTION STRUCTURE OF ESTERO DE PACO, MANILA CITY PHASE 2

South Manila DEO, National Capital Region

2025₱143.2M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2:PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS-FLOOD MGM'T PROGRAM-CONST./MAINT. OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS-CONST. OF SLOPE PROTECTION STRUCTURE OF ESTERO DE PACO, MANILA CITY PHASE 1

South Manila DEO, National Capital Region

2025₱143.1M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF SLOPE PROTECTION STRUCTURE ALONG PAGASA SABLAYAN TO VICTORIA ROAD, PALSIKAYON SECTION (PHASE 1), OCC. MINDORO

Region IV-B, Region IV-B

2023₱96.5M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF SLOPE PROTECTION STRUCTURE ALONG PAGASA SABLAYAN TO VICTORIA ROAD, PALSIKAYON SECTION (PHASE 2), OCC. MINDORO

Region IV-B, Region IV-B

2023₱96.5M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF SLOPE PROTECTION STRUCTURE ALONG PAGASA SABLAYAN TO VICTORIA ROAD, PALSIKAYON SECTION (PHASE 3), OCC. MINDORO

Region IV-B, Region IV-B

2023₱96.5M
Reported complete (DPWH)
View all 74 projects →

4. Implementation

Contract Amount

₱2,533,294.68

Progress

Reported complete (DPWH)

Start Date

November 18, 2020

Target End

December 7, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.