Flood Control and Drainage24I00012

CONSTRUCTION OF BANGON FLOOD CONTROL STRUCTURE ALONG BANGON RIVER, BARANGAY SAN JOSE (PHASE 2), PALO, LEYTE

CONSTRUCTION OF BANGON FLOOD CONTROL STRUCTURE ALONG BANGON RIVER, BARANGAY SAN JOSE (PHASE 2), PALO, LEYTE is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱169,698,424.12. Status: Past target date (DPWH On-Going). Contractor on record: EZJONES CONST INC. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

287 projects · ₱36.2B total · 7 flags

Other projects by this contractor

View all 287 projects →

4. Implementation

Contract Amount

₱169,698,424.12

Progress

Past target date (DPWH On-Going)

Start Date

March 6, 2024

Target End

May 4, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.