Bridges17NB0233

RETROFITTING/STRENGTHENING OF SAN LUIS POBLACION-MAGTUYON BRIDGE (DELTA BRIDGE), SAN LUIS, AGUSAN DEL SUR

RETROFITTING/STRENGTHENING OF SAN LUIS POBLACION-MAGTUYON BRIDGE (DELTA BRIDGE), SAN LUIS, AGUSAN DEL SUR is a DPWH-tracked public work in Agusan del Sur 1st DEO, Region XIII. Reported contract value: ₱30,699,880.04. Status: Reported complete (DPWH). Contractor on record: A T DUMLAO CONST INC FORMERLYANDONI T D. Figures trace to dpwh.

Agusan del Sur 1st DEO, Region XIII
Region: Region XIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Crossing Luna Flood Control, (K0+000-K0+121.6), along Bayugan-Esperanza Road, Agusan del Sur
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-17-0000252

₱628,443.00 · FY2017

Released to Leyte Normal University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱30,699,880.04

Progress

Reported complete (DPWH)

Start Date

January 15, 2018

Target End

December 10, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.