Construction of Flood Mitigation Structure22FC0079

Construction of Flood Control Structure (Phase 2) at Brgy. Mabilo, Labo, Camarines Norte

Construction of Flood Control Structure (Phase 2) at Brgy. Mabilo, Labo, Camarines Norte is a DPWH-tracked public work in LABO (CAMARINES NORTE), CAMARINES NORTE, Region V. Reported contract value: ₱34,299,455.10. Status: Reported complete (DPWH). Contractor on record: EUS CONST. Figures trace to sumbong.

LABO (CAMARINES NORTE), CAMARINES NORTE, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure (Phase 1) at Brgy. Mabilo, Labo, Camarines Norte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002900

₱1,325,575,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002430

₱43,000,000.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

193 projects · ₱9.1B total · 7 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY ALAWIHAO, DAET, CAMAR

Region V, Region V

2024₱144.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP): SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF FLOOD CONTROL, BARANGAY MOCONG, BASUD, CAMARINES NORTE (P

Region V, Region V

2023₱144.7M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MADUNGON RIVER, BARANGAY STA. ANA, SOLSONA, ILOCOS NORTE

Ilocos Norte 2nd DEO, Region I

2025₱141.4M
Past target date (DPWH On-Going)

ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY ALAWIHAO, DAET, CAMAR

Region V, Region V

2024₱140.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL IN BRGY. SAN ANTONIO, LABO-BRGY. FABRICA (MATOG

Region V, Region V

2024₱140.4M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP): SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF FLOOD CONTROL, BARANGAY MOCONG, BASUD, CAMARINES NORTE (P

Region V, Region V

2023₱140.3M
Past target date (DPWH On-Going)
View all 193 projects →

4. Implementation

Contract Amount

₱34,299,455.10

Progress

Reported complete (DPWH)

Start Date

March 21, 2022

Target End

May 4, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.