Buildings and Facilities20M00106

CONSTRUCTION OF MULTI-PURPOSE IN BARANGAY NEW CULASI, TULUNAN, NORTH COTABATO

CONSTRUCTION OF MULTI-PURPOSE IN BARANGAY NEW CULASI, TULUNAN, NORTH COTABATO is a DPWH-tracked public work in Region XII, Region XII. Reported contract value: ₱1,969,997.65. Status: Reported complete (DPWH). Contractor on record: TAJ BUILDERS AND SUPPLY. Figures trace to dpwh.

Region XII, Region XII
Region: Region XII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2020 GAA. DBM GAA FY2020

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

31 projects · ₱255.5M total · 0 flags

4. Implementation

Contract Amount

₱1,969,997.65

Progress

Reported complete (DPWH)

Start Date

March 19, 2020

Target End

July 16, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.