Flood Control and Drainage20PB0015

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF KARAGAWAN RIVER (UPSTREAM) FLOOD CONTROL, BRGY. BADDUAT, KABUGAO, APAYAO

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF KARAGAWAN RIVER (UPSTREAM) FLOOD CONTROL, BRGY. BADDUAT, KABUGAO, APAYAO is a DPWH-tracked public work in Apayao 1st DEO, Cordillera Administrative Region. Reported contract value: ₱18,903,751.05. Status: Reported complete (DPWH). Contractor on record: PRIME MASTER CONST AND DEV'T CORP. Figures trace to dpwh.

Apayao 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Karagawan River (upstream) Flood Control, Brgy. Badduat, Kabugao, Apayao
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Apayao 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

40 projects · ₱926.0M total · 0 flags

Other projects by this contractor

No sat.

NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/ NEW ROADS : PIDDIG, CARASI (ILOCOS NORTE)-CALANASAN-LANGNAO-KABUGAO ROAD - PACKAGE 2 (CONSTRUCTION OF CONCRETE BRIDGE), APAYAO

Apayao 1st DEO, Cordillera Administrative Region

2025₱141.7M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - CONSTRUCTION OF MISSING LINKS/NEW ROADS - CONSTRUCTION OF CONCRETE BRIDGE - SAN JOSE QUIBAL ROAD (BITAG-PEQUEÑO BR. 1), BAGGAO, CAGAYAN

Cagayan 1st DEO, Region II

2025₱98.3M
Ongoing (DPWH-reported)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - GUISING BR. (B01092LZ) ALONG MAHARLIKA HIGHWAY (CAGAYAN VALLEY RD)

Region II, Region II

2025₱67.5M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT-CONSTRUCTION OF MISSING LINKS / NEW ROADS ABRA-KALINGA-APAYAO ROAD (BULUAN-BANBAN-PUGUIN-SACPIL- PINUKPOK), PACKAGE 3, APAYAO

Apayao 1st DEO, Cordillera Administrative Region

2019₱56.3M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-BRIDGE PROGRAM-CONSTRUCTION OF NEW BRIDGES, CONSTRUCTION OF CONCRETE BRIDGE - TALLANG BRIDGE 1 (PHASE II) ALONG BAYBAYOG-BAGGAO-DALIN-STA. MARGARITA RD, BAGGAO, CAGAYAN

Cagayan 1st DEO, Region II

2024₱48.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS - CONSTRUCTION OF ALANNAY FLOOD CONTROL STRUCTURE ALONG ZINUNDUNGAN RIVER, LAS

Cagayan 2nd DEO, Region II

2025₱48.9M
Past target date (DPWH On-Going)
View all 40 projects →

4. Implementation

Contract Amount

₱18,903,751.05

Progress

Reported complete (DPWH)

Start Date

February 10, 2020

Target End

January 4, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.