Buildings and Facilities18OA0039

CONSTRUCTION(COMPLETION) OF TWO STOREY MPB DALAG ST. BLK 23 PH.2 AREA 1, BRGY. NBBS, NAVOTAS CITY

CONSTRUCTION(COMPLETION) OF TWO STOREY MPB DALAG ST. BLK 23 PH.2 AREA 1, BRGY. NBBS, NAVOTAS CITY is a DPWH-tracked public work in Malabon-Navotas DEO, National Capital Region. Reported contract value: ₱5,936,820.31. Status: Reported complete (DPWH). Contractor on record: VRV CONST AND TRADING. Figures trace to dpwh.

Malabon-Navotas DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱38,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Raising/Improvement of Drainage System along Dalagang Bukid St., Brgy. NBBS, Navotas City
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-18-0012972

₱177,925.00 · FY2018

Released to Division of Camarines Sur (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

195 projects · ₱2.0B total · 0 flags

Other projects by this contractor

No sat.

LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/ FACILITIES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE 2), PADRE GARCIA COMMUNITY HOSPITAL, PADRE GARCIA, BATANGAS

Batangas 4th DEO, Region IV-A

2021₱96.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BOLBOK INTEGRATED NATIONAL HIGH SCHOOL, BARANGAY BOLBOK, LIPA CITY, BATA

Batangas 4th DEO, Region IV-A

2024₱78.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TALISAY, LIPA CITY, BATANGAS

Batangas 4th DEO, Region IV-A

2024₱57.6M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/ FACILITIES, CONSTRUCTION/ COMPLETION OF MULTI-PURPOSE BUILDING (COMMUNITY HOSPITAL) AT BRGY. CASTILLO, PADRE GARCIA, BATANGAS

Batangas 4th DEO, Region IV-A

2020₱38.4M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/ FACILITIES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT MAXIMO T. HERNANDEZ MEMORIAL NATIONAL HIGH SCHOOL AND MALAININ ELEMENTARY SCHOOL, IBAAN, BATANGAS

Batangas 4th DEO, Region IV-A

2020₱38.4M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM, CONSTRUCTION/ REPAIR/ REHABILITATION/ IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/ FACILITIES, CONSTRUCTION OF MULTI- PURPOSE BUILDING (BUREAU OF FIRE), LIPA CITY, BATANGAS

Batangas 4th DEO, Region IV-A

2020₱38.0M
Reported complete (DPWH)
View all 195 projects →

4. Implementation

Contract Amount

₱5,936,820.31

Progress

Reported complete (DPWH)

Start Date

March 8, 2018

Target End

July 20, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.