Roads21FG0064

REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROAD ALONG TINAMBAC - SIRUMA ROADK0542+970.00 - K0543+154.00SIRUMA, CAMARINES SUR

REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROAD ALONG TINAMBAC - SIRUMA ROADK0542+970.00 - K0543+154.00SIRUMA, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 4th DEO, Region V. Reported contract value: ₱9,800,000.00. Status: Reported complete (DPWH). Contractor on record: IA FERRER CONST. Figures trace to dpwh.

Camarines Sur 4th DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Baliguon River, Goa, Camarines Sur
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Camarines Sur 4th DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

55 projects · ₱692.2M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM - KATUPARAN) JCT. GUIJALO-SAN VICENTE ROAD LEADING TO SAN VICENTE PORT. STA.7+600.00 - STA.8+700.00CARAMOAN, CAMARINES SUR

Camarines Sur 4th DEO, Region V

2023₱49.6M
Reported complete (DPWH)
No sat.

CONSTRUCTION / IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM - KATUPARAN) JCT. GUIJALO-SAN VICENTE ROAD LEADING TO SAN VICENTE PORT - STA.6+350.00 - STA.7+600.00, CARAMOAN, CAMARINES SUR

Camarines Sur 4th DEO, Region V

2022₱49.6M
Reported complete (DPWH)
No sat.

CONSTRUCTION ROAD, BRGY. MAYBATO, PARACALE TO BRGY. MALANCAO - BASUD, LABO, CAMARINES NORTE

Camarines Norte DEO, Region V

2025₱48.0M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM - KATUPARAN) JCT. GUIJALO - SAN VICENTE ROAD LEADING TO SAN VICENTE PORTSTA.5+000.00 - STA.6+350.00 CARAMOAN, CAMARINES SUR

Camarines Sur 4th DEO, Region V

2021₱47.2M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF FLOOD MITIGATION STRUCTURECARAPDAPAN CREEK BARANGAY ABO, BARANGAY SAN MIGUEL, BARANGAY CASUNA, TIGAON, CAMARINES SUR

Camarines Sur 4th DEO, Region V

2025₱38.7M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION / IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) PRESENTACION TO CARAMOAN ROAD LEADING TO ISLETS, BEACHES, ROCK FORMATION, CAVES, LAGOON, CARAMOAN NATURAL PARK

Camarines Sur 4th DEO, Region V

2023₱31.0M
Reported complete (DPWH)
View all 55 projects →

4. Implementation

Contract Amount

₱9,800,000.00

Progress

Reported complete (DPWH)

Start Date

September 15, 2021

Target End

February 6, 2022

5. Audit