Roads16AD0149

REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGED BASED ON PAVEMENT MANAGEMENT-4(HDM-4), JCT. STA. LUCIA-SALCEDO ROAD, K0340+000-K0341+000 AND K0341+918-K0342+000

REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGED BASED ON PAVEMENT MANAGEMENT-4(HDM-4), JCT. STA. LUCIA-SALCEDO ROAD, K0340+000-K0341+000 AND K0341+918-K0342+000 is a DPWH-tracked public work in Ilocos Sur 2nd DEO, Region I. Reported contract value: ₱31,276,488.42. Status: Reported complete (DPWH). Contractor on record: R S SEPIAN CONST. Figures trace to dpwh.

Ilocos Sur 2nd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Cavite Bridge1 and Cavite Bridge 2, MNR, Sta. Lucia, Ilocos Sur
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-17-0001386

₱277,462,000.00 · FY2017

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

100 projects · ₱2.3B total · 0 flags

Other projects by this contractor

View all 100 projects →

4. Implementation

Contract Amount

₱31,276,488.42

Progress

Reported complete (DPWH)

Start Date

May 25, 2017

Target End

November 20, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.