Buildings and Facilities22OB0175

CONSTRUCTION OF CYBER BATTALION AND NETWORK ENTERPRISE TECHNOLOGY BATTALION ADMIN BUILDING WITH PARKING AND OUTSIDE DEVELOPMENT, TAGUIG CITY

CONSTRUCTION OF CYBER BATTALION AND NETWORK ENTERPRISE TECHNOLOGY BATTALION ADMIN BUILDING WITH PARKING AND OUTSIDE DEVELOPMENT, TAGUIG CITY is a DPWH-tracked public work in Metro Manila 1st DEO, National Capital Region. Reported contract value: ₱47,485,723.10. Status: Reported complete (DPWH). Contractor on record: PASCAL CONST. Figures trace to dpwh.

Metro Manila 1st DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Maintenance and Rehabilitation of Flood Control Structure along Ilugin River, Pasig City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Metro Manila 1st DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱47,485,723.10

Progress

Reported complete (DPWH)

Start Date

February 8, 2022

Target End

January 23, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.