Construction of Flood Mitigation Structure22ID0044

Construction of Marabong Flood Control Structure and Drainage System, Marabong River Basin, Sta. 0+000 - Sta. 0+300 (Downstream), Burauen, Leyte

Construction of Marabong Flood Control Structure and Drainage System, Marabong River Basin, Sta. 0+000 - Sta. 0+300 (Downstream), Burauen, Leyte is a DPWH-tracked public work in BURAUEN (LEYTE), LEYTE, Region VIII. Reported contract value: ₱48,999,538.87. Status: Reported complete (DPWH). Contractor on record: FAIRCHILD BUILDERS & DEVELOPERS INC. Figures trace to sumbong.

BURAUEN (LEYTE), LEYTE, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Marabong Flood Control Structure and Drainage System, Marabong River Basin, Sta. 0+000 - Sta. 0+300 (Downstream), Burauen, Leyte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002647

₱550,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0006795

₱50,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003176

₱50,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-22-0005719

₱20,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003040

₱2,500,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱48,999,538.87

Progress

Reported complete (DPWH)

Start Date

March 21, 2022

Target End

March 15, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.