Buildings and Facilities21J00137

PROPOSED CONSTRUCTION OF EVACUATION CENTER, MOLAVE, ZAMBOANGA DEL SUR

PROPOSED CONSTRUCTION OF EVACUATION CENTER, MOLAVE, ZAMBOANGA DEL SUR is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱27,345,139.72. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: GENETIAN BUILDERS AND ENT INC FORMERLY: GENETIAN BUILDERS. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2021 GAA. DBM GAA FY2021

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

484 projects · ₱13.7B total · 3 flags

4. Implementation

Contract Amount

₱27,345,139.72

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

January 7, 2022

Target End

October 3, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.