Construction of Revetment22AI0106

Construction of Flood Control Structure along Cabulandayan River, Brgy. San Eugenio, Natividad, Pangasinan

Construction of Flood Control Structure along Cabulandayan River, Brgy. San Eugenio, Natividad, Pangasinan is a DPWH-tracked public work in NATIVIDAD (PANGASINAN), PANGASINAN, Region I. Reported contract value: ₱29,390,746.66. Status: Reported complete (DPWH). Contractor on record: RIVBROS CONST FACTORS & DEVELOPMENT. Figures trace to sumbong.

NATIVIDAD (PANGASINAN), PANGASINAN, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Cabulandayan River, Brgy. San Eugenio, Natividad, Pangasinan
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002947

₱753,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003035

₱40,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003014

₱10,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱29,390,746.66

Progress

Reported complete (DPWH)

Start Date

February 24, 2022

Target End

August 12, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.