Construction of Flood Mitigation Structure22ED0115

Construction of Bucayao River Control Calapan City

Construction of Bucayao River Control Calapan City is a DPWH-tracked public work in CITY OF CALAPAN (CAPITAL) (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B. Reported contract value: ₱38,392,547.71. Status: Reported complete (DPWH). Contractor on record: LUMEL GLENN CONST. Figures trace to sumbong.

CITY OF CALAPAN (CAPITAL) (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Victoria, Or. Mindoro
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002356

₱1,389,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002909

₱866,223,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002986

₱150,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002621

₱2,000,000.00 · FY2022

Source

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction of Bucayao River Control, Calapan Cit

₱38,392,547.71 · LUMEL GLENN CONSTRUCTION

4. Implementation

Contract Amount

₱38,392,547.71

Progress

Reported complete (DPWH)

Start Date

May 26, 2022

Target End

December 2, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.