Buildings and Facilities16NA0042

CONSTRUCTION OF 2 UNITS 2 STY 8-CL MAGALLANES NHS, MAGALLANES, AGUSAN DEL NORTE 2ND L.D

CONSTRUCTION OF 2 UNITS 2 STY 8-CL MAGALLANES NHS, MAGALLANES, AGUSAN DEL NORTE 2ND L.D is a DPWH-tracked public work in Agusan del Norte DEO, Region XIII. Reported contract value: ₱23,559,393.72. Status: Reported complete (DPWH). Contractor on record: REYROSE CONST. Figures trace to dpwh.

Agusan del Norte DEO, Region XIII
Region: Region XIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱23,559,393.72

Progress

Reported complete (DPWH)

Start Date

August 28, 2016

Target End

March 25, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.