Flood Control and Drainage24PJ0024

24PJ0024: FLOOD MANAGEMENT PROGRAM -CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF EMPHOLLE TAWANG SIS FLOOD CONTROL STRUCTURE, MAYOYAO, IFUGAO

24PJ0024: FLOOD MANAGEMENT PROGRAM -CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF EMPHOLLE TAWANG SIS FLOOD CONTROL STRUCTURE, MAYOYAO, IFUGAO is a DPWH-tracked public work in Ifugao 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱29,400,000.00. Status: Reported complete (DPWH). Contractor on record: ROVINA CONST. Figures trace to dpwh.

Ifugao 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Empholle Tawang SIS Flood Control Structure, Mayoyao, Ifugao
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Ifugao 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

33 projects · ₱358.8M total · 0 flags

Other projects by this contractor

No sat.

25PJ0006: ASSET PRESERVATION PROGRAM- REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS-BANAUE-MAYOYAO-A LISTA-ISABELA BDRY RD - K0377 + 243 - K0377 + 365, K0378 + 442 - K0378 + 486, K0378 + 509 - K0378 +

Ifugao 2nd DEO, Cordillera Administrative Region

2025₱35.9M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS TOURISM ROAD INFRASTRUCTURE PROGRAM TRIP ACCESS ROAD LEADING TO AMMUNG FESTIVAL, YAO JIA XI DRAGON FRUIT FARM, DOMINGOS INTEGR

Ifugao 2nd DEO, Cordillera Administrative Region

2023₱29.1M
Reported complete (DPWH)
No sat.

21PJ0003: LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION OF ALIMIT-MAGATAWA BARANGAY ROAD, ALIMIT, MAYOYAO, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2021₱24.8M
Reported complete (DPWH)
No sat.

23PJ0008: BASIC INFRASTRUCTURE PROGRAM (BIP)-INTERJURISDICTIONAL ROADS AND/OR BRIDGES (OR, ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)-CONSTRUCTION OF CHAPAY BRIDGE, INWALOY, MAYOYAO, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2023₱24.8M
Reported complete (DPWH)
No sat.

22PJ0008: NETWORK DEVELOPMENT PROGRAM - OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS - BANAUE-MAYOYAO-A LISTA-ISABELA BDRY RD - K0394 + 455 - K0395 + 643, K0395 + 801 - K0396 + 070, K0397 + 000 - K0397 + 865, K0398 + 000 - K0398 + 500, AGUINALDO, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2022₱22.8M
Reported complete (DPWH)
No sat.

23PJ0020: CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES-CONSTRUCTION OF ROAD, JUNCTION NALBU TO AYA

Ifugao 2nd DEO, Cordillera Administrative Region

2023₱19.6M
Reported complete (DPWH)
View all 33 projects →

4. Implementation

Contract Amount

₱29,400,000.00

Progress

Reported complete (DPWH)

Start Date

June 20, 2024

Target End

April 12, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.