Buildings and Facilities18BD0014

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. LANNA, SOLANA, CAGAYAN, 3RD LD

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. LANNA, SOLANA, CAGAYAN, 3RD LD is a DPWH-tracked public work in Cagayan 3rd DEO, Region II. Reported contract value: ₱1,920,325.86. Status: Reported complete (DPWH). Contractor on record: JOHN 6:51 BUILDERS. Figures trace to dpwh.

Cagayan 3rd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control System (Downstream), Natappian, Solana, Cagayan
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROII-18-0002813

₱6,117,152.00 · FY2018

Released to Regional Office - II (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

90 projects · ₱398.0M total · 0 flags

4. Implementation

Contract Amount

₱1,920,325.86

Progress

Reported complete (DPWH)

Start Date

February 4, 2018

Target End

May 4, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.