Roads20IA0073

CONCRETING/REHABILITATION OF ROAD LEADING TO ALMERIA NATIONAL HIGH SCHOOL

CONCRETING/REHABILITATION OF ROAD LEADING TO ALMERIA NATIONAL HIGH SCHOOL is a DPWH-tracked public work in Biliran DEO, Region VIII. Reported contract value: ₱972,380.00. Status: Reported complete (DPWH). Contractor on record: QYT CONST AND SUPPLIES. Figures trace to dpwh.

Biliran DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Santol Flood Control along Biliran Circumferential Road (Phase 4), Biliran, Biliran
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Biliran DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱972,380.00

Progress

Reported complete (DPWH)

Start Date

October 15, 2020

Target End

January 2, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.