Roads21N00014

LIANGA COASTAL BYPASS ROAD (SDCR ALTERNATE ROUTE), SURIGAO DEL SUR

LIANGA COASTAL BYPASS ROAD (SDCR ALTERNATE ROUTE), SURIGAO DEL SUR is a DPWH-tracked public work in Region XIII, Region XIII. Reported contract value: ₱101,324,994.80. Status: Reported complete (DPWH). Contractor on record: CM TAN CONST. Figures trace to dpwh.

Region XIII, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2021 GAA. DBM GAA FY2021

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱101,324,994.80

Progress

Reported complete (DPWH)

Start Date

August 6, 2021

Target End

June 6, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.